Continuing track works

The preparation to continue the work on the track № 59 – a main communication route in the Shed – started in the late winter period. We focused on recovering the ballast from between the ties. The work was organized in such a manner that the periods of the track being out of order were as short as possible. Yet unfavourable weather or flu season caused some delays to the initial plan.

Between February and March 2017, we signed the agreement with City of Skierniewice to receive the fund of 14 500 PLN to repair the most dilapidated parts of the tracks. After removing the ballast, we could unscrew the rails and move them aside to recover the remains of old wooden ties. This way we made a free room for a backhoe loader to dig the new track trench, spread a fresh layer of ballast and lie down the heavy concrete ties and rails.
Finally we were able to resupply the ballast between the ties. We intend to continue the works after purchasing more ties for this purpose.