Last track works this year

67363318_2895638577174031_5805980822737518592_o

Still in November we managed to complete the last track works. The scope of this year’s repair was replacement of ties under track № 14 and № 15 in front of the roundhouse. We already reported the progress of works on track № 14. Since then we finished the fastening and ballasting of both tracks. Next thanks to a selfless help of the FAC Rail all tracks leading to the roundhouse repaired for the last two years were properly tamped and regulated. The last activity was to move the concrete crossing blocks back on their place.

We would would like to express our gratitude to FAC Rail. We are happy that another company from Skierniewice representing the railway maintenance branch is supporting us. We would also like to thank the City of Skierniewice for the financial support of the track works in the amount of 16 800 PLN.